Project 2 - Cherry Lane/Western Avenue

PUBLIC NOTICES

Cherry Lane Construction Notice - 6/4/08
Cherry Lane Construction Notice - 4/11/08
Cherry Lane - Western Avenue Improvement Project - Project Information Meeting - 2/7/08

WEEKLY UPDATES

October 26-November 2

Plote Construction completed clean up and punchlist items for all construction work on Cherry Lane.  Thanks to all residents for your patience during this construction season and we hope that you are all pleased with the finished product.

October 19-October 25

The striping for Cherry Lane has been completed for Cherry Lane.  The striping includes all center line and edge line striping.  All crosswalks and stop bars were included as well.  The remaining shared bike lane symbols are to be installed at a later date.

October 12-October 18

The final asphalt surface course was completed for Cherry Lane between Landwehr Road and Greenbriar Lane.  Plote Construction completed the remaining punchlist items for the project and final regrading and reseeding of all parkways has been completed.

October 5 - October 12

Plote construction continued work on punch list items including various underground storm sewer modifications and the replacement of curb.  All preparation work for paving of the surface course has been completed and paving of the asphalt surface course is anticipated to commence on Wednesday, October 15.

September 28 - October 4

Plote Construction completed the grinding of butt joints and the binder course.  The contractor continued the completion of punch list items for the completion of the project.  This included the completion of brick paver installation in the bump outs east of Western Ave. and some limited landscaping work.

May 2008
June 2008
July 2008
August 2008
September 2008


2007 Weekly Updates

PROJECT DESCRIPTION

This project generally consists of the pavement reconstruction of Cherry Lane from Landwehr Road to Greenbriar Lane and Western Avenue from Walters Avenue to Dundee Road.  The pavement reconstruction includes new full depth bituminous pavement, new concrete curb and gutter, partial sidewalk removal and replacement, and topsoil/seeding parkway restoration.  The existing roadways section will generally be maintained which includes two thru travel lanes and a parallel parking lane on both sides of the thru lanes.  Curb and gutter/pedestrian “bump outs” will be constructed at various intersections.  These “bump outs” will serve as traffic calming devices as well as reducing the in-road travel distance for pedestrian crossing the street.

PROJECT CONTACTS

Resident Engineer

Kevin Wilson, P.E.

Christopher B. Burke Engineering, Ltd.

Cell: 847-291-9135

 

EXHIBITS

None at this time.

 

RESIDENT NOTIFICATIONS

None at this time.

 